Skip to main content

Information

Address 56610 East End Road

All dried in for winter…….

All dried in for winter…….

All dried in for winter……. Dave saved the day, and got the deck covered Friday. Not that anyone would notice but the extended section in back and front are pitched deck areas. When the building gets built,  those deck areas extend 4’ beyond the outside walls. Although the hip roof will have a 5’ overhang […]

Making some progress on the foundation

Making some progress on the foundation

Making some progress on the foundation slow, but accurate as possible, to get the floor framing polygon as right as possible. This all done over this strong, old, settled, out of square foundation. This has to be done for the upper floor to be square plumb and level. There will be blocking between the old […]